WEST END BREWERY, SOUTH AUSTRALIA

PROJECT HYDE PARK

CLIENT: LION

YEAR: 2013 -2015

SECTOR: BREWING

MAJOR PROJECT TEAM

Lion chose Foodline Projects as the preferred mechanical installation contractor for the entire Hyde Park Project.
Valued at more than $10m, the two-year project was a huge success with Foodline’s management staff working closely with Lion project engineers to finalise the most effective design options.

PROJECT SCOPE

  • New brewhouse supplied by Krones
  • New Cider Plant using refurbished fermenters from Swan Brewery in Perth
  • New Crossflow Filter
  • Strip out a part of the Swan brewhouse, relocate, reassemble and install
  • Install 3 new CIP Plants
  • Bulk chemical handling plant
  • Cellar Refurbishment
  • Boiler upgrade
  • Strip out existing brewhouse
  • New sugar upgrade
  • Water farm relocation and installation
  • Temporary pipe relocation

SAFETY FIRST APPROACH

The Hyde Park project ran for 2 years with 35 specialised welders from TFG Group onsite full time. To ensure the safety of their employees, sub-contractors and operations staff, Foodline Projects employed a dedicated onsite safety officer to oversee the project. As a result, 68,000 man hours were worked with zero safety incidents, MTIs or LTIs. This safety first approach was particularly pertinent given that the total shut down time for the installation was only 7 weeks.